Agoura Hills Construction
Week of November 30, 2026
Reminder
In observance of the Thanksgiving holiday, there will be no work or roadway closures from Thursday, November 26 through Friday, November 27. We wish the community a safe and happy Thanksgiving.
Agoura Road Utility Work
Utility work will continue in phases along eastbound Agoura Road between Oak Crest Drive and Reyes Adobe Road. Crews will continue installing irrigation crossings and water lines within the public right-of-way and will begin lighting relocation at the entrance of the Advanced Water Purification Facility. Roadway restriping will follow the utility work.
Dates/Times
Weekdays, from 7 a.m. to 3:30 p.m. Utility work is anticipated to continue for the next several weeks, with roadway restriping to follow later in December.
Traffic Impacts
Within designated work areas, eastbound Agoura Road will be temporarily reduced to one lane. Motorists and cyclists should anticipate traffic shifts, modified bicycle access, and possible delays. Access to nearby businesses and residences will generally be maintained, although brief restrictions may be necessary.
Construction is a dynamic process. This information and the project schedule are subject to change due to weather, field conditions, and other factors.

Advanced Water Purification Facility (AWPF)
Construction will continue in phases at the AWPF site. Crews continue underground electrical, plumbing, and process piping work; concrete work for pipe trenches and future treatment structures; site preparation for the future chemical facility; and grading and drainage improvements behind the site retaining wall.
Dates/Times
Facility construction is planned during daytime weekday hours.
Construction is a dynamic process. This information and the project schedule are subject to change due to weather, field conditions, and other factors.
Neighboring City Activities
Pipeline construction will continue in phases along Agoura Road in Westlake Village. Work includes nighttime construction at Lindero Canyon Road and Agoura Road, as well as daytime pipeline installation and temporary paving between Lakeview Canyon Road and Greengate Court. Temporary lane closures, traffic shifts, turn restrictions, and possible delays are anticipated. Crews will work to minimize nighttime noise impacts as much as possible.
Contact Us
Questions? Contact the Project Outreach Team at (818) 245-4440 or ourpureh2o@lvmwd.gov.
Want to learn more about Pure Water construction activities in Agoura Hills? Sign-up for Agoura Hills construction updates below!

Sign Up for Agoura Hills Construction Updates
Past Construction Updates


